MOCKUP v1.0 New Financial Details tab on Bridge Overview — running bills entry, financial vs physical progress chart, financial % calculation Prepared 17-05-2026 · For client review
Dashboard List of Bridges Sangani Vala Stop Bridge · Overview

Sangani Vala Stop Bridge

In Progress SH-87 (Anand–Khambhat Road)
Anand District · Vasad–Khambhat Stretch · Ch. 24+750 · Sub-Divn: M/s Patel Construction Co. (Anand)
Work Value (Sanctioned)
₹ 6,75,00,000
Work Order Date
15-03-2025
Stipulated Completion
14-09-2026
Length / Spans
142 m · 4 Spans
Total Work Amount
₹ 6,75,00,000
Sanctioned · incl. all items
Total Bills Paid
₹ 4,52,78,500
5 running bills · last on 12-05-2026
Financial Progress
67.08%
Physical Progress
71.50%
Sub Division Amount is the contractor's measured value excluding Star Rate and Price Adjustment components — it is the figure used to compute Financial Progress against Total Work Amount.

Physical vs Financial Progress

Cumulative % at each running-bill milestone

Last financial update: 12-05-2026
5 days ago · RB #5
Physical Progress
Financial Progress
Financial lagging physical by 4.42% — typical for bill-cycle timing

Running Bills

Inline-editable · Sub Division Amount excludes Star Rate & Price Adjustments

RB No. Bill Date Sub Division Amount
excl. Star Rate / Price Adj
Star Rate Adj Price Adjustment Total Bill Amount Cumulative % Status
Totals →

Financial Progress Calculation

As of 12-05-2026 (RB #5)
Financial Progress % = Σ Sub Division Amount ÷ Total Work Amount × 100
= ₹ 4,52,78,500 ÷ ₹ 6,75,00,000 × 100 = 67.08 %
Only the Sub Division Amount column contributes to financial progress. Star Rate and Price Adjustment amounts are tracked separately and shown in the Total Bill Amount but excluded from the percentage.